Despite gas industry forecasts that South and Southeast Asia will drive global demand for liquefied natural gas (LNG), LNG-fired power plants and import terminal projects in these regions have advanced far more slowly than expected.
Between 2021 and 2026, more than half of LNG-fired power projects and import terminals in the Philippines, Vietnam, Thailand, and Bangladesh have been canceled or shown no notable progress.
Recent developments in global LNG markets, as well as equipment and currency markets, have exacerbated execution risks for LNG-to-power projects in emerging economies and weakened the revenue security on which non-recourse project financing depends.
Higher LNG costs and project execution risks, combined with falling renewable energy and battery storage costs, suggest that expectations of rapid, sustained LNG demand growth in emerging Asian markets warrant closer scrutiny.
In 2021, the Institute for Energy Economics and Financial Analysis (IEEFA) published a regional analysis of liquefied natural gas (LNG)-to-power project developments across seven Asian markets. The report found that despite billions of dollars in proposed investments in both LNG import terminals and power plants, only a small fraction was likely to materialize, due to fundamental constraints related to economics, financial capacity, infrastructure, and policy.
This analysis is an update to the previous report. It examines the pace of progress on LNG developments in Asia, the drivers of success, and the outstanding challenges to getting projects off the ground. Coverage focuses on four prospective gas and LNG demand growth markets in Asia, namely Thailand, the Philippines, Vietnam, and Bangladesh.
In these four markets, IEEFA surveyed 92 proposed LNG-fired power projects worth an estimated USD109.2 billion and 44 LNG import terminals valued at USD21 billion. Key findings include:
Section 1 of this report provides an overview of recent developments affecting LNG demand growth across emerging Asia. It considers how recurring LNG crises, gas turbine shortages, and high currency requirements are impacting the viability of gas power plant projects and power development plans across Asia.
Section 2 begins with an overview of gas project developments since 2021 across the four countries surveyed, detailing the value of projects that were completed, canceled, inactive, or remain under development. It then provides a more detailed analysis of the project data for the four countries surveyed and highlights the country-specific challenges that ongoing projects must navigate to achieve completion.