IEEFA Update: Will Southern Company Refund Mississippi Ratepayers for Failed $7.5 Billion Kemper ‘Clean Coal’ Experiment?

June 23, 2017
David Schlissel

Call it what you will: fiasco, debacle, calamity, misadventure.

But not a surprise. Georgia-based Southern Company and its regulators in Mississippi were warned years ago that the experimental and now infamous “clean coal” Kemper power plant project was a shot in the dark. They kept at it anyway, pushing the price tag to $7.5 billion, well over twice the approved costs, with construction still undone years beyond the promised completion date.

Executives at Southern and its subsidiary Mississippi Power County and a majority of the members of the Mississippi Public Service Commission pursued Kemper—at huge expense to ratepayers—even after being warned about what would happen.

I know because I warned them years ago.

In explaining the project’s risk to the commission I described several likely eventualities. Among them:

  • That the cost of building the plant would be significantly higher than what the company was telling the commission in 2009 and using in its viability analyses;
  • That natural gas prices would be substantially lower than the company had used in its viability analyses, meaning that a coal-reliant plant would find it hard to compete;
  • That because the plant was using a first-of-a-kind IGCC (integrated gas combined cycle) technology it would not operate as well as the company hoped.

All of these risks have materialized, which is why the public service commission announced this week that it had had enough and that the Kemper “clean coal” experiment was over and that the plant henceforth will burn natural gas instead.

“The message is pretty clear,” Paul Patterson, an equity analyst who follows Southern at Glenrock Associates LLC, told the Wall Street Journal. “Mississippians don’t want to pay for a ticket on a plane that isn’t going to fly.”

The commission has a say-so, of course, because part of its job is to protect ratepayers from utility companies. And although this particular action comes a little late in the game, the reason for that is that new commissioners were elected to the board in November 2015, replacing the group that had approved the deal.  The relentless work of the Sierra Club in Mississippi, challenging the costs of Kemper, helped build public support for a regime change at the commission and for the unanimous vote this week in favor of consumers.

As the Associated Press reported the other day, “Southern Co. shareholders have so far absorbed $2.7 billion in losses. Customers could ultimately be asked to pay $2.4 billion.”

Why didn’t Southern Company executives listen when red flags were raised? Perhaps because a combination of arrogance and greed were at play as executives expected that customers would pay costs that would be incurred along the way and were confident that they were developing a new product that they could market around the world.

Why else would the company have rejected all of the warnings associated with the project’s many risks?

David Schlissel is IEEFA’s director of resource planning analysis.

Read Testimony: Kemper County IGCC Project here.

RELATED POSTS:

IEEFA Wyoming: Bid to Export ‘Clean Coal’ to Japan Rings False

IEEFA Op-Ed: Blind Faith in Fossil-Fuel Industries Will Strand Economies, Communities, Workers

Kemper Power Plant, a Debacle That Should Never Have Been Built

David Schlissel

David Schlissel is an IEEFA analyst with 50 years of experience as an economic and technical consultant on energy and environmental issues. 