The pipeline is owned by Dominion (48%), Duke Energy (47%), and Southern Company (5%), which together formed Atlantic Coast Pipeline LLC (ACP-LLC).
These project owners intend for the upfront capital cost of building the project, currently estimated at $6.5 to $7 billion, to be recovered through transportation rates from the companies that contract with ACP-LLC to ship natural gas on the pipeline. Ninety-six percent of the capacity on the pipeline was contracted when the pipeline was first proposed to FERC.
In its order approving the Atlantic Coast Pipeline, the Federal Energy Regulatory Commission specifically declined to comment on whether the contracts (known as precedent agreements) that regulated utilities had entered into with affiliates to ship gas on the pipeline were prudent.
The Atlantic Coast Pipeline (ACP) is a 600-mile, 42-inch natural gas pipeline currently under construction to bring natural gas from northern West Virginia to Virginia and North Carolina. The project is being built by a joint venture of Dominion (48%), Duke Energy (47%), and Southern Company (5%). Its construction was approved by the Federal Energy Regulatory Commission in October 2017.
The project was originally projected to cost $5.1 billion. Cost overruns to date have raised the cost of the project by about 30% to $6.5 to $7 billion, excluding financing costs. But cost overruns are not the only challenge faced by the project.
The biggest threat to the project’s profitability may come if and when the project is ever completed. The demand outlook for gas has changed dramatically since the project’s inception and much of the project’s original justification has evaporated. Indications are that the project’s affiliated utility customers may struggle to convince state regulators to pass the full cost of pipeline transportation agreements through to utility customers. Indeed, the project does not represent good value to the ratepayer.
This briefing discusses the considerable headwinds faced by the Atlantic Coast Pipeline. Key findings include:
We recommend several questions investors could be asking management in order to obtain a clearer view of the project’s value.
Press release: IEEFA report: The vanishing case for the Atlantic Coast Pipeline
Please view full report PDF for references and sources.