Skip to main content

Key Findings

Project Tundra received $16.9 million in 2020 from the U.S. Department of Energy (DOE) and $9.8 million in the fall of 2019 to start the project, instead of evaluating whether the project is viable in the first place

Minnkota has pledged it will not pursue Project Tundra if it “substantially increases electric rates.”

Executive Summary

Square Butte Electric Cooperative and Minnkota Power Cooperative own and operate Unit 2 at the Milton R. Young (Young Unit 2) coal-fired plant in Center, N.D. The cooperatives are proposing to retrofit the 43-year-old, 455 megawatt-capacity unit with equipment to capture 90% of its carbon dioxide (CO2) emissions and either sequester the CO2 underground or sell it for use in enhanced oil recovery (EOR) activities.

The proposal, dubbed the Tundra Project by its supporters, received $16.9 million this spring from the U.S. Department of Energy (DOE) to complete the permitting work needed for two underground injection wells and then build them. Last fall, the project was awarded $9.8 million in DOE funds to complete a front end engineering and design (FEED) study for the project, with the goal of developing “design, costing and performance data needed to commence project financing activity,” as well as a final project schedule.

In short, this DOE money is being used to start the project, instead of evaluating whether the project is viable in the first place. This is critical, as Minnkota has pledged it will not pursue Project Tundra if it “substantially increases electric rates.”

IEEFA’s analysis of the project shows it faces significant risks and uncertainties that could undermine its economic viability and lead to higher electric rates for the ratepayers of the cooperatives that buy power from Minnkota or Minnesota Power. These include:

  • Uncertainty over the cost of adding the new carbon capture facility and associated project infrastructure;
  • The potential that significant problems will be experienced during the scaling up of the planned Fluor capture technology from its small tested size (5 megawatts to 40 megawatts) to a commercial-scale 455MW coal plant;
  • Uncertainty whether the project will capture enough CO2 so that it can be financed entirely thru federal 45Q tax credits. If not, Minnkota would be forced to borrow additional funds to build and, perhaps, operate the project, thereby incurring unexpected costs that will be borne by ratepayers, not investors;
  • Uncertainty over the cost of capturing the CO2 produced by the plant;
  • Uncertainty over the cost of sequestering captured CO2;
  • Young Unit 2 is not a low-cost generator and it is quite possible, if not likely, that the cost of the electricity from the plant will be substantially higher if it is retrofitted for carbon capture. Ratepayers already are paying far more for electricity from the plant than they would if their co-ops purchased the same amount of power from competitive wholesale markets. This can be expected to get worse in future years, especially if Project Tundra is undertaken; and
  • Uncertainty whether there will be a viable market for using the captured CO2 for EOR activities.

Minnkota has acknowledged that carbon capture, utilization and storage technology has not been adequately demonstrated for nationwide use.2 However, it is gambling that Project Tundra can succeed because of its “unique geographical location.”3 If it loses this bet, the ratepayers of the 11 cooperatives that own Minnkota and Square Butte may have to pay substantially higher rates for power from Young Unit 2, or indeed, for a failed project.

Square Butte and Minnkota Power would be well-served by taking the time afforded by the DOE grants to weigh the risks carefully—going forward risks putting their co-op customers on the hook for significant construction cost overruns and long-term responsibility for higher operations and maintenance costs. A better option would be to follow the lead of Great River Energy which earlier this year announced plans to retire the younger, larger and better running Coal Creek station, close Young Unit 2, and embrace the renewable energy transition by building cleaner, lower-cost wind with storage to meet its capacity needs.


Press release: Ratepayers face risks with Project Tundra’s retrofit of aging N.D. coal-fired plant

David Schlissel

David Schlissel is an IEEFA analyst with 50 years of experience as an economic and technical consultant on energy and environmental issues. 

He has testified as an expert witness before regulatory commissions in more than 35 states and before the U.S. Federal Energy Regulatory Commission and the Nuclear Regulatory Commission.

Go to Profile

Dennis Wamsted

At IEEFA, Dennis Wamsted focuses on the ongoing transition away from fossil fuels to green generation resources, focusing particularly on the electric power sector.

Go to Profile

Join our newsletter

Keep up to date with all the latest from IEEFA