The Kemper IGCC Project: Cost and schedule risks

November 01, 2012
David Schlissel
Download Full Report

Key Findings

Kemper is not more than 70% complete, as MPC has claimed. Its overall construction and engineering is only about 40-45% complete.

Although the Project's direct construction cost is capped, further cost increases will increase the non-mine financing costs that ratepayers will have to pay.

Executive Summary

David Schlissel

David Schlissel is an IEEFA analyst with 50 years of experience as an economic and technical consultant on energy and environmental issues. 