French renewable energy developer Neoen has filed its development application for the huge $3 billion Goyder South wind, solar and storage project in South Australia which includes a proposed big battery than it nearly 10 times bigger than the expanded “Tesla big battery” at Hornsdale.

The plan proposes a total of 1,200MW of wind energy, 600MW of solar PV, and 900MW/1800MWh of battery storage, an “extremely large” battery as Neoen describes it that will dwarf the 150MW/194MWh “Tesla” battery known officially as the Hornsdale Power Reserve.

Each stage would be delivered in three equal tranches of 400MW wind, 200MW solar and 300MW/600MWh of battery storage. Combined, they would generate around 4.8 terawatt hours of zero emissions power each year, nearly doubling the current output of wind and solar in the state, and taking South Australia close to the Liberal government’s net 100 per cent renewables target just on its own.

Neoen insists that the first stage is likely to go ahead regardless of any significant grid upgrades, but admits that the second and third stages would be contingent on the new transmission line between South Australia and NSW, known as Project EnergyConnect, going ahead. 

The French developer says the wind facility will be made up of up to 163 turbines, suggesting a capacity of 7.3MW per turbine – by far the biggest announced in Australia to date. It says these machines will have a maximum hub height of 160 meres, a maximum blade length of 80m, and an overall maximum height (tip height) of 240m.

The lithium-ion batteries would deliver 900MW with two hours of storage, and associated infrastructure for connection to the electricity grid would include three substations, access tracks, underground connection cabling and transmission lines.

[Giles Parkinson]

More: Neoen files plans for $3bn wind and solar farm with battery 10 times bigger than Hornsdale 