More Delays on Marquee Nuclear Project in Finland

Bloomberg News:

Olkiluoto-3, able to power about 3 million homes, will be delayed until May 2019 from its previously expected to start at the end of next year, according to Teollisuuden Voima Oyj, the Helsinki-based utility that will operate the unit. Areva SA, the supplier, said it needed more time to adjust the production schedule.

Plagued by cost overruns and legal tangles, the delay is the latest setback for the 1,600-megawatt reactor meant to provide cheap power to companies from Finnish papermakers UPM-Kymmene Oyj and Stora Enso Oyj to a Google Inc. server farm. The nation last year had to import a quarter of its electricity in the wholesale market, where prices for delivery to Finland are about 21 percent higher than the Nordic-region average.

Olkiluoto-3 was billed by Areva and Siemens AG as a showcase for next-generation EPR-reactor technology when construction started in 2005. The project’s initial 3 billion-euro ($3.5 billion) cost has swelled to more than 8 billion euros.

The latest delay is for adjustments based on information from a similar reactor being built in China, as well as a more cautious assessment of how quickly the unit will reach full production, an Areva spokesman said by phone. Fuel loading is scheduled for August 2018 and the first connection to the grid is in the following December.

The new reactor technology is proving tricky even in state-owned Areva’s home market. The cost of an EPR at Flamanville in France has tripled since construction started in 2007 in a project that’s six years behind schedule.

When construction began, Olkiluoto-3 was to be the world’s biggest reactor and the first with EPR technology. That mantle may now go to China, which plans to start two 1,660-megawatt EPR-reactors in Taishan within the next 18 months.

The Finnish project’s parties are suing each other over the delays. TVO won part of its case against Areva-Siemens in July at the International Chamber of Commerce in Paris. A final arbitration decision is expected early next year.

Areva has been delisted from the stock exchange by the French state, which injected 2 billion euros in the entity in July to help it complete the Olkiluoto project and pay back some loans. Areva is also due to sell a majority stake in its reactor business to Electricite de France SA by the end of the year to raise further funds.

More: Finland’s 10-Year Wait for a Nuclear Reactor Just Got Longer